Fast Track Projects
A decade and a half ago we found ourselves with quite a challenge: due to a unique set of circumstances stemming from a planned event at our client’s property we had ten months to completely renovate a 12,000 square foot home. This required a creative approach.
Managing the capricious New England weather was our chief challenge; by building an enclosure over the site – a system of steel beams and boat wrap – we were able to work through a tough Rhode Island winter and rainy spring.
Such a tight timetable also required vigilant schedule management, constant communication with the design team, and rigorous management of subcontractors.
Happily, Parker Construction delivered this project on time and has since completed approximately 15 similarly fast-track projects, adjusting and reimagining our process to fit each project’s unique logistical and schedule requirements.

The
Beginning

Foundations + Frames

Staging for the Winter

Building Truss

Wrapping the Igloo

Meanwhile, Under the Tent...

All's Calm on the Building Front

The
Unveiling

Cleanup for Summer

Mission Complete